Dismantled Machines in Several Shipments: Vietnam Rules

Dismantled machinery shipped in several lots is classified as one machine if the List and deduction tracking sheet are registered first (Circular 85/2026).

Quick answer: A dismantled machine imported in several shipments is still classified under the code of the complete machine (Rule 2(a)), provided the List and the deduction tracking sheet are registered with customs before the first shipment, under Circular 85/2026/TT-BTC.

Six key-point cards on importing dismantled machinery in several shipments: classified as the complete machine, List registration required, two forms, submit before the first shipment, deduction for each shipment, and Lists registered before 15 September 2026 continue under the old rules.

A factory buys a production line from abroad. The machines are too big, so the supplier dismantles them and packs them into many containers across three or four sailings, sometimes from two different suppliers. The first shipment brings only the machine frames; the motors and electrical cabinets come later. The question is: which code should each shipment be declared under?

If each shipment is declared on its own, each part is classified as a separate item: the steel frame under one code, the motor under another, the electrical cabinet under a third. Each code has a different duty rate, and some parts may be caught by their own management requirements. The law offers a way to avoid this: registering a List of machinery and equipment (Danh mục).

Rule 2(a): a dismantled machine is still a machine

Rule 2(a) of the six General Interpretative Rules of the HS system allows goods presented unassembled or disassembled to be classified as the complete, assembled article. Article 8 of Circular 85/2026/TT-BTC applies this rule to machinery and equipment that is dismantled because of packing, storage or transport requirements.

When a machine arrives in a single shipment, customs can see all the parts at once. When it arrives in several shipments, from one or more sources, and is cleared at one or more locations, the List registration procedure in Article 9 must be followed.

Composite machines and functional units: a choice of classification

Article 7 covers composite machines (two or more machines fitted together) and functional units under Chapters 84, 85 and 90. When a composite machine or functional unit arrives in several shipments (from one or more sources), the declarant may choose:

- To classify each machine or piece of equipment separately; or
- To classify under Legal Notes 3, 4 and 5 to Section XVI, treating the whole unit as one machine according to its principal function.

The second option also requires List registration under Article 9. Calculate the duty both ways before choosing, because in some cases classifying machine by machine works out better.

What goes into the registration dossier?

Under Clause 1 of Article 9, the dossier consists of two items:

- The List of machinery, equipment, parts and loose components, on form 01/ĐKDMTB/2025.
- The deduction tracking sheet, on form 02/PTDTL-DMTB/2025.

Both forms are in Appendix V of Circular 121/2025/TT-BTC.

Where and when should it be submitted?

- Before registering the import declaration for the first shipment.
- At whichever customs office is most convenient for the business.
- Through the customs electronic system. If the system cannot yet receive a particular field, submit a digitally signed scan, or submit in person.

If the dossier is in order, customs confirms the List and the deduction tracking sheet within no more than 3 working days. The business receives 1 original of the List and 1 original of the sheet. Build these 3 days into your plan; do not wait until the vessel is about to berth before you submit.

What happens with each shipment?

- The customs office handling the shipment compares the goods actually imported with the List, classifies them, and deducts the quantity imported on the sheet.
- If a shipment is cleared at a different office from where the List was registered, the business brings the original List and sheet there to present them.
- For the final shipment, customs records on the sheet that all goods under List No. … have been imported.

Amendments and lost documents

- To amend or supplement the List: submit the amended List and sheet to the office where it was registered, before the declaration for the first shipment or before the declaration for the shipment containing the amended part.
- Lost List: send a written request to the registering office for a replacement. Customs reissues it within no more than 3 working days.
- Lost deduction tracking sheet: the business draws up a new sheet itself, listing the declaration numbers and quantities already imported, takes responsibility for its contents, and submits it to the customs office handling the next shipment for cross-checking.

For any List not fully imported within the registered time limit, customs will assess the risk and may re-examine the classification of shipments already cleared.

Lists registered before 15 September 2026

Circular 85/2026 takes effect from 15 September 2026. Under Clause 2 of Article 16, Lists registered before that date continue to follow Circular 14/2015/TT-BTC until all the goods have been imported. Businesses part-way through importing do not need to register again.

A note on used machinery

If the production line consists of used machinery under Chapters 84 and 85 imported for production, it must also meet the machine-age conditions in Circular 56/2026/TT-BKHCN, effective from 5 September 2026. This is a separate procedure, which we will cover in an article on importing used machinery.

Our experience

The most common snag with List registration is naming. The List is drawn up from the drawings, while the invoice for each shipment is prepared by the supplier's sales department, which names items differently each time. If customs cannot match them, you have to explain.

So our advice is to build the List from the supplier's master packing list, numbering each part. Then send it back to the supplier and require the invoice and packing list for every shipment to use exactly those names and numbers. Each shipment should state clearly which List number it belongs to and which parts have arrived.

One more small point: store the originals of the List and the deduction tracking sheet as important documents. If they are lost, they can be replaced, but it takes time, exactly when the goods are waiting at the port.

Legal basis

- Circular 85/2026/TT-BTC on the classification of goods, effective from 15 September 2026: Articles 7, 8 and 9; Article 16, Clause 2. Official Gazette No. 409, 18 July 2026: https://congbao.chinhphu.vn/van-ban/thong-tu-so-85-2026-tt-btc-469982.htm
- Circular 121/2025/TT-BTC (effective 1 February 2026), Appendix V: forms 01/ĐKDMTB/2025 and 02/PTDTL-DMTB/2025. https://congbao.chinhphu.vn/van-ban/thong-tu-so-121-2025-tt-btc-468755.htm
- Circular 56/2026/TT-BKHCN on importing used machinery and equipment, effective from 5 September 2026. https://congbao.chinhphu.vn/van-ban/thong-tu-so-56-2026-tt-bkhcn-470423.htm

Is your factory about to import machinery in several shipments? Send the master packing list and the contract to [email protected] or WhatsApp/Zalo +84 937 639 365. We will check how the List should be registered and send a quote within 2 business hours.

Does this affect your shipment? Send us your documents and we will check and quote within 2 business hours.

Get a quote
Get quote Facebook ZaloZalo +84 937 639 365 Call +84 937 639 365