China's 2027 Spring Festival: nine days off (5–13 Feb)
China has set its 2027 Spring Festival holiday from 5 to 13 February, with make-up workdays on Sundays 31 Jan and 14 Feb. How importers should plan orders.
Quick answer: China's 2027 Spring Festival holiday runs nine days, from 5 to 13 February 2027, with make-up working days on Sunday 31 January and 14 February, according to the State Council schedule published on 5 November 2026. Importers should confirm orders and production early so goods ship before the break.

On 5 November 2026, the General Office of China's State Council published the 2027 public holiday schedule. The Spring Festival (Chinese New Year) break lasts nine days. For shop owners and businesses importing from China, this is the key date for planning orders for Tet and the start of the year.
China's official 2027 holidays
- New Year's Day: Friday 1 January to Sunday 3 January 2027, 3 days.
- Spring Festival (春节): Friday 5 February 2027 (New Year's Eve) to Saturday 13 February 2027 (the 8th day of the first lunar month), 9 days in total. Sundays 31 January and 14 February are make-up working days.
- Qingming Festival: Saturday 3 April to Monday 5 April 2027, 3 days.
Why should importers pay attention?
This is the official schedule. In practice, many factories set their own dates and may stop taking orders or stop production earlier, or restart later, than the official calendar. Domestic carriers, warehouses and forwarding offices in China also slow down over this period.
That typically leads to:
- Orders placed close to the holiday may not be produced in time and slip to after the break.
- Cargo rushing out before the holiday makes vessel and truck space on China – Vietnam routes tighter.
- After the holiday, factories need time to get workers back and return to normal output.
How should you plan orders?
The simplest approach is to count back from the date you need goods in your warehouse:
- Start from the date you need the goods, minus customs clearance and local delivery time in Vietnam.
- Subtract transit time from China (sea, road or air).
- Subtract the time from factory to port or border gate.
- Subtract the production time confirmed by the supplier.
That gives you the date to confirm the order. If it falls in late January or during the holiday, order earlier or accept delivery after the break.
What to do now
- Ask suppliers directly: the last date for orders before the holiday, the date the factory closes and the date it actually reopens.
- Goods for Tet sales in Vietnam: confirm orders and book transport early, because Vietnam's 2027 Tet holiday also falls in early February.
- Goods for the new year: agree a post-holiday delivery date in writing, with terms for late delivery.
- Have documents ready (contract, invoice, packing list) so goods can move as soon as they leave the factory.
Working with suppliers over the holiday
Get holiday dates in writing or in a dated message, not just verbally. If goods need pre-shipment inspection, book it before the holiday, because inspectors are hard to schedule close to the break.
Sources
- General Office of the State Council of China, notice on the arrangement of some public holidays in 2027 (国务院办公厅关于2027年部分节假日安排的通知), dated 5 November 2026, published by Xinhua: https://www.news.cn/20261105/ac6792e1565949dc8e7d6e8261b9a055/c.html
If you are planning shipments from China for Tet, send us the cargo details and the date you need the goods via WhatsApp/Zalo +84 937 639 365 or email [email protected], and we will reply with a quote and transport schedule within 2 working hours.